To check PET preform quality, compare samples from every cavity with the preform drawing and the customer standard. Six checks cover most problems:

1. Weight
Total shot weight and the weight of each cavity.
2. Neck finish
Thread, sealing surface and support ring against the finish drawing.
3. Wall and concentricity
Even wall all around the preform, with the core centred.
4. Clarity and colour
No white haze, streaks or colour difference.
5. Contamination and gate
No black specks, bubbles or foreign particles; a clean, short gate.
6. Blow result
Sample bottles blown from the preforms meet the bottle specification.

Why preform quality matters

The neck is final when the preform leaves the mold, so a neck defect becomes a leaking or badly capped bottle. The body decides how the bottle blows: an uneven wall or a hazy zone shows up as thin spots, weak bottles or rejects at the blow molder.

Preforms are also made many at a time. A worn neck split or a cold hot-runner nozzle in one cavity produces a defect on every cycle until it is found, so inspection always tracks results by cavity number.

What to check on a PET preform

Weight
Weigh the full shot and individual preforms by cavity number. Shot weight shows the machine's stability; cavity-to-cavity differences point to the mold and hot runner.
Neck finish dimensions
Check thread diameter, sealing surface, support ring and height with calipers, go/no-go gauges or a profile projector. Tolerances come from the finish drawing.
Length, wall thickness and concentricity
Measure overall length and the wall around the circumference. A thicker wall on one side means the core is off centre (core shift), which gives uneven bottle walls.
Clarity, colour and crystallinity
Look for white haze, especially at the gate and the neck, and compare colour between cavities and against an approved sample.
Contamination
Check for black specks, foreign particles and bubbles on a light box or against a dark background.
Gate area
Check gate length, stringing, holes and white crystallised spots. The gate becomes the centre of the bottle base.
Stress
A polariscope shows stress patterns as coloured or dark bands. Compare against an approved sample: the patterns depend on preform design, so they are hard to judge without a reference.
Blow test
Blow sample bottles on the intended blowing process. A preform can pass its own checks and still blow badly.
PET preform weighed on a precision balance
Weight check on a precision balance.
PET preform mounted on a dial-gauge fixture for wall and concentricity measurement
Wall thickness and concentricity measured with a dial gauge.

Inspection methods and tools

Most plants combine manual checks at the machine with laboratory checks on samples. High-volume plants add camera inspection on the conveyor. Choose the method by what it finds and how often you need it:

MethodWhat it findsWhen it makes sense
Precision balanceShot and cavity weight variationEvery plant, at start-up and through each shift
Calipers and go/no-go neck gaugesNeck, support ring and length out of toleranceEvery plant, on samples from each cavity
Wall thickness and concentricity gaugeUneven wall, core shiftStart-up, mold changes and regular sampling
Light box and visual checkHaze, specks, bubbles, colour streaks, gate defectsContinuous, at the machine
PolariscopeStress patterns and changes from the approved sampleStart-up, process changes and complaints
Inline camera inspectionVisual and some dimensional defects on every preformHigh-volume production where 100% checking is required
Blow testHow the preform performs as a bottleNew molds, new resin lots and acceptance
Green PET preforms viewed under polarised light showing stress patterns
Polarised-light check: compare the patterns with an approved sample.

PET preform defects: material and drying

One symptom can have several sources. The tables below list where to look first, not a single cause. Where a defect needs process adjustment, the PET injection molding guide covers process troubleshooting.

DefectWhat you seeWhere to look first
Bubbles or splaySmall bubbles in the wall, silver streaks on the surfaceResin moisture and dryer performance
Haze throughout the preformCloudy body, loss of clarity in all cavitiesDrying, resin lot changes and regrind share
Brittle preformsCracks at the gate or neck when dropped or squeezedResin moisture, excessive regrind, overheated melt
YellowingYellow tint compared with the approved sampleDrying temperature and time, regrind, melt heat history
Colour streaksStreaks or shade differencesMasterbatch dosing, carrier compatibility and mixing
Foreign particlesVisible inclusions in the wallResin storage, open containers, regrind and conveying

PET preform defects: machine and process

DefectWhat you seeWhere to look first
Short shotIncomplete thread or support ring in all cavitiesShot size, injection and transfer settings
Shot weight variationTotal weight drifts from shot to shotScrew recovery, check ring condition, holding pressure
Black specksDark particles, often after stops or colour changesDegraded material in the barrel or hot runner, residence time, purging
Burn marksBrown or yellow marks near the gateMelt temperature, residence time, shear at the nozzle
Flash in all cavitiesThin fins at the parting line or neckClamping force against injection and holding pressure
White crystallised zonesOpaque white areas in the body or at the gateCooling time and chilled-water temperature
Oval preformsBody or neck not roundCooling time and handling while the preform is still hot

PET preform defects: mold

DefectWhat you seeWhere to look first
Cavity-to-cavity weight imbalanceThe same cavities are always heavier or lighterHot-runner zone temperatures, nozzle and valve condition
Core shift, uneven wallWall thicker on one side; uneven bottle wallsCore alignment, core cooling, wear of locating tapers
Gate defectsLong gate, stringing, hole or white spot at the gateValve gate and nozzle tip condition, gate cooling
Neck flash or damaged threadFins along the thread split line, deformed threadNeck split wear, damage or alignment
WatermarksRipples or marks on the surfaceCondensation on cold mold surfaces in humid air
ScratchesLines on the body or neckEjection, stripper ring and take-out handling

A defect that appears in one or a few cavities usually points to the mold or hot runner; a defect in every cavity usually points to the material or the machine settings.

Sampling: how often and how many

Follow your customer's standard where one exists. Where it does not, most plants build a plan around these moments:

At start-up
A full shot, checked cavity by cavity, before production is released.
During each shift
Regular weight and visual checks, with full dimensional checks at set intervals.
Cavity rotation
Over a day or a week, every cavity number is checked, not only the first few.
After any change
New resin lot, colour change, mold service, stoppage or process change.
Retained samples
Keep labelled samples from each lot for complaints and comparison.

PET preform inspection checklist

Print this table and adapt frequencies and tolerances to your preform drawing and customer standard.

ItemMethodToolFrequency (example)Record
Shot weightWeigh full shotPrecision balanceStart-up, then every few hoursWeight, time, lot
Cavity weightWeigh by cavity numberPrecision balanceStart-up and daily rotationWeight per cavity
Neck finishMeasure thread, sealing surface, support ringCalipers, go/no-go gaugesStart-up and each shiftPass/fail or values per cavity
Length and wallMeasure length and wall around the bodyHeight gauge, wall gaugeStart-up and dailyValues per cavity
AppearanceHaze, specks, bubbles, colourLight boxContinuousDefects found, cavity number
GateLength, holes, white spotsVisual, calipersEach shiftPass/fail per cavity
StressCompare with approved samplePolariscopeStart-up and after changesPass/fail, photo
Blow testBlow sample bottlesBlow molderNew mold, new resin lot, acceptanceBottle results

Inspecting preforms during mold trials and acceptance

A new mold or machine is accepted against preforms, so the inspection plan should be agreed before the trial. HWAMDA records preform weight, cavity count and cycle time during customer mold trials before shipment.

Agree these points in advance: the preform drawing and weight tolerance, the neck finish standard and gauges, the target cycle, the number of active cavities, how many sample shots are kept, how cavities are identified, and whether sample bottles will be blown.

FAQ

Frequently asked questions

How do you check the quality of a PET preform?

Take samples from every cavity and check weight, neck finish dimensions, wall thickness and concentricity, clarity and colour, contamination and the gate, then blow sample bottles. Compare the results with the preform drawing and customer standard, and record them by cavity number.

What causes black specks in PET preforms?

Most black specks are degraded PET that has stayed too long in a hot zone, such as the barrel, check ring, nozzle or hot runner, and breaks loose, often after stops or colour changes. Contaminated resin or regrind is the other common source.

Why are some preforms hazy or white near the gate?

White haze at the gate is usually crystallised PET from too little cooling at the gate or a gate area that stays too hot. Haze throughout the preform points more to moisture, degraded resin or cooling in general.

Why do preform weights vary between cavities?

If the same cavities are always heavier or lighter, look at the hot runner zone temperatures, nozzle and valve condition and cavity cooling. If the total shot weight drifts, look at the machine: screw recovery, check ring and holding pressure.

What is a polariscope used for in preform inspection?

A polariscope shows internal stress in clear PET as coloured or dark patterns. It is used to compare production preforms with an approved sample, because a change in the pattern can show a change in the process or mold.

How often should preforms be inspected?

Follow the customer standard. A common approach is a full cavity-by-cavity check at start-up, regular weight and visual checks each shift, a rotation that covers every cavity over time, and a recheck after any change of resin lot, colour, mold or process.